How is building height measured on a sloping block?
Building height on a sloping block is measured from Datum Ground Level (DGL) to the highest point of the building.
ACT Planning’s Advisory Note 09 specifically explains that DGL is the base used for calculating building height. It is determined from an authorised field survey from the time of subdivision or grant of the lease. If that information is unavailable, a registered surveyor determines the best estimate having regard to surrounding ground levels. For a DA, the DGL is normally shown on the field survey submitted with the application.
This means the building height on a sloping site is assessed against the surveyed DGL, rather than simply measuring from the lowest or highest point of the current ground.
Reference: ACT Advisory Note 09 – Building Heights, Storeys and Basements – Building heights, storeys and basements
Short Answer
Building height on a sloping block is measured vertically from the surveyed Datum Ground Level (DGL) to the highest point of the building. DGL is established by survey and provides the baseline for assessing building height.
Detailed Explanation
Building height is determined by reference to Datum Ground Level (DGL). ACT Planning defines building height for Territory Plan purposes as the vertical distance between DGL and the highest point of the building.
DGL is established from an authorised field survey undertaken at subdivision or when the lease was granted or, where such information is unavailable, from a registered surveyor's best estimate having regard to surrounding levels. The Surveyor-General Guideline 03 provides the detailed surveying methodology for establishing DGL, including for infill sites.
No minimum block size does not remove the need for planning assessment.
Would you like to know what these rules mean for your property?